Answer:
1. $2,296
2. $19.58
3. Total labor cost = Fixed cost + (variable cost × employee hour)
Step-by-step explanation:
The computations are shown below:
1. The fixed cost would be
= High labor cost - (High employee hours × Variable rate per hour)
= $10,324 - (410 hours × $19.58)
= $10,324 - $8,028
= $2,296
2. Variable rate per hour = (High labor cost - low labor cost) ÷ (High employee hours - low employee hours)
= ($10,324 - $6,800) ÷ (410 hours - 230 hours)
= $3,524 ÷ 180 hours
= $19.58
3. The cost formula would be
Total labor cost = Fixed cost + (variable cost × employee hour)
= $2,296 + ($19.58 × employee hour)