Answer:
B. 3 more.
Explanation:
If the time for each of the machines working alone to complete the job = x hours then
6 * 1/x = 1/12
1/x = 1/12/6 = 1/72
x = 72 days.
So we have the equation
y * 1/72 = 1/8
y = 72/8 = 9.