198k views
0 votes
In order to calculate the _______ , the project manager must take into consideration the status of each activity or task in the project.

A. 50-50 rule
B. project scope
C. EVM measures
D. 0-100 rule

User Ffritz
by
6.3k points

1 Answer

1 vote

Answer:

C. EVM measures

Step-by-step explanation:

There are two rules for completion of the project which are as follows:

a. 0-100 rule: In this rule, no money is received for a work unless it has been completed.

b. 50-50 rule: Based on this, 50% is received when work is started and the remaining 50% is received when work is finished.

The project scope deals the project planning in respect to the cost, time, goals and objectives

And, the EVM stands for earned value management which measures the performance of the projects or we can say the status of each task in the project that represents the completion and in process. It helps in forecasting

User Simon White
by
5.8k points