32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the

same work by 16 workers working 8 hours per day?

User Srbhkmr
by
2.7k points

1 Answer

4 votes

Answer:

45 days

Explanation:


32 * 30 * 6 / (16 * 8)


5760 / 128


\boxed{\green{ = 45}}