A job can be done by 30 men in 15 days. How long would it take 10 men to do the same job?​

User Quarkonia
by
4.2k points

1 Answer

3 votes

Answer:

45 days

Explanation:

Based on the giving information, 30*15/10.

Reduce the fraction by canceling the greatest common factor: 3*15 = 45