164k views
4 votes
How many bags of concrete are needed to fill the path 1m3 requires 106 x 20kg bags of concrete The pond is 7m diameter and the path around is 2m 50mm deep

User Realtime
by
5.3k points

1 Answer

3 votes

Answer:

300 Bags

Explanation:

According to the Question,

  • Given that, We are laying a concrete border around a circular pond. The pond is 7 metres in diameter and is surrounded by a path 2 metres wide.

The radius of the pool = 3.5 m; the overall radius including the border = 3.5 + 2 = 5.5m

  • The area of the concrete border

overall area - pool area = border area(A)

A = π×5.5² - π×3.5²

A = 56.55 sq m

  • The concrete needs to be 50 millimetres deep.

the volume of the concrete, change 50 mm to .05 m

56.55 * 05 = 2.8275 cu/meters

  • We are using premixed bagged concrete.

1 cubic metre requires 106 x 20 kg bags.

  • So For the number of bags

106 * 2.8275 = 299.715 ≈ 300bags

  • 300 bags of 20 kg of premixed concrete We need
User Samuel Robert
by
5.1k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.