Answer:
Product ABC
Step-by-step explanation:
Calculation to determine the maximize profit, they should first fill the demand for if the company's constraint is machine hours.
Product ABC's CM per unit= $10/5 minutes
Product ABC's CM per unit=$2 per minute of machine time
Product XYZ's CM per unit=$15/10 minutes
Product XYZ's CM per unit= $1.50 per minute of machine time
Therefore If the company's constraint is machine hours, to maximize profit, they should first fill the demand for PRODUCT ABC because it has the HIGHEST CM PER UNIT.