Answer: 0.48 minutes
Step-by-step explanation:
Takt time = Net time available / Daily demand
Net time available is number of minutes in a shift so:
= 8 hours * 60 minutes
= 480 minutes
Daily demand = 1,000 units
Takt time = 480 / 1,000
= 0.48 minutes