Mccabe Corporation uses the weighted-average method in its process costing. The following data pertain to its Assembly Department for September. Percent Complete Units Materials ConversionWork in process, September 1 2,500 55 % 10 %Units started into production during September 9,900 Units completed during September and transferred tothe next department 9,000 Work in process, September 30 3,400 75 % 25 %Compute the equivalent units of production for both materials and conversion costs for the Assembly Department for September using the weighted-average method.