If 3 men can paint 4 houses in 5 days , how many days does it take for 7 men paint 14 houses ??? help me plz
asked
Sep 14, 2022
50.5k
views
4
votes
If 3 men can paint 4 houses in 5 days , how many days does it take for 7 men paint 14 houses ??? help me plz
Mathematics
high-school
Ham Dong Kyun
asked
by
Ham Dong Kyun
7.5k
points
answer
comment
share this
share
0 Comments
Please
log in
or
register
to add a comment.
Please
log in
or
register
to answer this question.
1
Answer
3
votes
Answer:
3men = 4houses= 5days
7men= 14houses= x days
14÷7 = 2days
Willi Mentzel
answered
Sep 19, 2022
by
Willi Mentzel
8.0k
points
ask related question
comment
share this
0 Comments
Please
log in
or
register
to add a comment.
Ask a Question
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.
8.8m
questions
11.4m
answers
Other Questions
What is .725 as a fraction
How do you estimate of 4 5/8 X 1/3
A bathtub is being filled with water. After 3 minutes 4/5 of the tub is full. Assuming the rate is constant, how much longer will it take to fill the tub?
Write words to match the expression. 24- ( 6+3)
The cost of 5 similar digital cameras and 3 similar video cameras is 3213. Each video camera costs 4 times as much as each digital camera. John buys a digital camera and a video camera. How much does he
Twitter
WhatsApp
Facebook
Reddit
LinkedIn
Email
Link Copied!
Copy
Search QAmmunity.org