Answer:
$15.00 per direct labor hour
Step-by-step explanation:
predetermined manufacturing overhead rate = Budgeted overheads ÷ Budgeted Activity
= $30,000 ÷ 2,000 hours
= $15.00
thus,
The predetermined manufacturing overhead rate per direct labor hour for the year is $15.00 per direct labor hour