Answer:
$31
Step-by-step explanation:
Given the following information,
Total factory overhead costs = $1,745,300
Direct labor hours = 56,300
To calculate the predetermined manufacturing overhead rate, we will make use of the formula below;
Predetermined manufacturing overhead rate = Total estimated overhead costs for the period / Total amount of allocation base
= $1,745,300 / 56,300
= $31
Therefore, the predetermined overhead rate to apply to factory overhead is $31