269,388 views
17 votes
17 votes
Brown Corporation uses a job-order costing system with a single plant-wide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data: Total machine-hours 40,000 Total fixed manufacturing overhead cost $344,000 Variable manufacturing overhead per machine-hour $3.9 Recently, Job M759 was completed. It required 60 machine-hours. The amount of overhead applied to Job M759 is closest to: (Round your intermediate calculations to 2 decimal places).

User Miigon
by
3.3k points

1 Answer

4 votes
4 votes

Answer:

See below

Step-by-step explanation:

With regards to the above, first we need to compute the fixed manufacturing overhead.

Fixed manufacturing overhead

= Total fixed manufacturing overhead ÷ Total machine hours

= $344,000 ÷ 40,000

= $8.6 per machine hour

Calculation of overhead applied to Job M759

Variable manufacturing overhead

= 60 machine hours × $3.9

= $234

Fixed manufacturing overhead

= 60 machine hours × $8.6

= $516

Therefore, total overhead applied to job M759 is $750

User Ehsan Khaveh
by
2.6k points