A 14 km road needs repaired. Workers can repair 3 1/2 km of the road per week. How many weeks will it take to repair the road?

User Majoris
by
4.3k points

1 Answer

6 votes

Answer:

3×1/2 = 1.5km per week

14÷1.5=9.33 if you round it it would take 9weeks