The amount of time an activity can be delayed without delaying the early start date of any immediately following activities is known as a _____.a.forward passb.backward passc.fast trackingd.free slack

1 Answer

3 votes

Answer:

free slack

Step-by-step explanation:

Free slack is the amount of time that an activity can be delayed without affecting the early start date of any activities that are dependent on it. It is a measure of the flexibility and potential for overlapping of activities in a project schedule.