Answer:
Results are below.
Step-by-step explanation:
To calculate the direct material price and quantity variance, we need to use the following formulas:
Direct material price variance= (standard price - actual price)*actual quantity
Direct material price variance= (5.9 - 5.65)*26,600
Direct material price variance= $6,650 favorable
Direct material quantity variance= (standard quantity - actual quantity)*standard price
Direct material quantity variance= (7,300*3.6 - 26,600)*5.9
Direct material quantity variance= $1,888 unfavorable