On a service call, your technician used one contractor the cost you $17.50, one capacitor that cost you$6.75, one motor that cost you $134, and miscellaneous items that cost you a total of $11.15. Time spent on the job was 3.5 hours and your labor cost is $28.50 per hour. Overhead for your company is 38% and you want to make 22% net margin. What must you charge the customer to achieve your profit target?