Answer choices:
A. less than or equal to 125 pounds
B. more than 225 pounds
C. more than 125 pounds but less than or equal to 175 pounds
D. more than 175 pounds but less than or equal to 225
Answer:
A. Less than 125 pounds
Step-by-step explanation:
We have the demand = 50 pounds
The standard deviation is given as 5
Service level is 95%
Z critical value is 1.645
Lead time is 2
We calculate reorder time as
RD = DMD * LT + ss
Reorder point = RD
Dmd is demand
Ss is safety stock
Lt lead time
Safety stock = 1.645x 5 x √2 = 12
Reorder = 50x2+12 = 112
112 is less than 125 so answer choice is A