g In the Shaping Department of Crane Company the unit materials cost is $2.00 and the unit conversion cost is $1.50. The department transferred out 7000 units and had 1500 units in ending work in process 20% complete. If all materials are added at the beginning of the process, the total cost to be assigned to the ending work in process is $1050. $5250. $3000. $3450.

User Photoionized
by
2.6k points

1 Answer

16 votes
16 votes

Answer:

$3,450

Step-by-step explanation:

Step 1 : Equivalent units of production in work in process

Materials = 1,500 x 100 % = 1,500

Conversion Costs = 1,500 x 20 % = 300

Step 2 : Cost to be assigned to the ending work in process

Materials (1,500 x $2.00) $3,000

Conversion (300 x $1.50) $450

Total $3,450

Conclusion

the total cost to be assigned to the ending work in process is $3,450.