Cost pools should be charged to responsibility centers by using: Multiple Choice budgeted amounts of allocation bases because the behavior of one responsibility center should influence the allocations to other responsibility centers. actual amounts of allocation bases because the behavior of one responsibility center should influence the allocations to other responsibility centers. actual amounts of allocation bases because the behavior of one responsibility center should not influence the allocations to other responsibility centers. some other approach. budgeted amounts of allocation bases because the behavior of one responsibility center should not influence the allocations to other responsibility centers.

User Mina Gabriel
by
3.0k points

1 Answer

6 votes
6 votes

Answer:

budgeted amounts of allocation bases because the cost allocation to one responsibility center should not influence the allocations to others.

Step-by-step explanation:

The budgeted amount of allocation bases would be measured at the starting of the period and the same would be applied or used to charge the cost pool for the responsibility centers

Hence, according to the given situation, the above represent the answer

And, the same should be relevant