One crew can seal a parking lot in 14 hours and another in 18 hours. How longwill it take to seal the parking lot if the two crews work together?

User Orujimaru
by
4.4k points

1 Answer

4 votes

Let the amount of work be L.

Therefore, the rate of work of the first team:


(L)/(14)

Similarly, the work rate of the second team is:


(L)/(18)

Therefore, the combined rate of both crews is given by:


(L)/(14)+(L)/(18)=(8L)/(63)

The time is given by:


\text{ time }=\frac{\text{ amount of work}}{\text{ rate}}

Therefore,


\text{ time }=L/(8L)/(63)=L*(63)/(8L)=(63)/(8)=7hours\text{ }53\text{ min}

Hence, the required time is 7 hours 53 minutes

.