Answer:
NPW = -$136.539 million
The negative net present value means that the project is not financially feasible, and therefore the company does not approve or pursue this investment.
Step-by-step explanation:
Data Given:
Initial cost = $150 million
Annual cost = $15 million
Annual revenue = $18 million
salvage value = $0
Time period = 8 years
MARR = 15%
Calculate Net present worth:
NPW = -$150 million + ($18 million - $15 million) (P/A, 15%, 8)
(P/A, 15%, 8) = 4.487
NPW = -$150 million + ($3 million * 4.487)
NPW = -$150 million + $13.461 million
NPW = -$136.539 million
The negative net present value means that the project is not financially feasible, and therefore the company does not approve or pursue this investment.