how many workers will.be needed to complete a task in 9 days given that it takes 12 days for 3 workers to complete the same task

User AFOC
by
6.0k points

1 Answer

3 votes

The task can be finished in 12 days for 3 workers. For this condition that the work can be done by 3 workers in 12 days, we have


task=12days*3workers=36\text{ worker-days}

If we have 9 working day to complete the task, we will be needing


\frac{36\text{ worker days}}{9\text{ days}}=4\text{ workers}

It takes 4 workers to finish the same task in 9 days.