If 4 electricians can wire some new houses in 20 days, how many electricians would be required to do the job in 10 days?

a. 30
b. 8
c. 45
d. 2

User Fernando Lopes
by
2.7k points

1 Answer

21 votes
21 votes

Answer:

2

Explanation:

20/2 = 10

4/2 = 2