Answer:
3.5 days
Explanation:
If it takes 7 pupils 5 days, then it would take 1 pupil 7 times as long, or 35 days.
1 pupil alone cleans the auditorium is 35 days.
10 pupils work 10 times faster than 1 pupil, so 10 pupils take 3.5 days.