Answer: 26.1 minutes
Step-by-step explanation:
The cycle time is calculated by the formula:
= Production time available / Desired output
Production time available = 1 hour as production is per hour.
1 hour = 60 minutes
Desired output is the demand per hour from the process
Cycle time = 60 / 2.3
= 26.1 minutes