Answer:
Top down looks at the project as a total unit, whereas bottom up looks at individual tasks.
Step-by-step explanation:
in the case when the top down and the bottom up predicted the usage of the parametric ratio that could be expected that the difference should be that the top down recognize the project and treated as the total unit while on the other hand the bottom up recognized the project on the person to person task or indiviudal task
Therefore the above statement should be considered