Answer:
0.8333
Explanation:
Given :
Mean, X = 100
Lower Specification Limit, LSL = 100 - 10 = 90
Upper Specification Limit, USL = 100 + 10 = 110
Standard Deviation, σ = 4
The process capability index, Cpk;
Cpk = Min[(X - LSL) / 3σ; (USL - X) /3σ]
Cpk = Min[(100 - 90) / 12 ; (110 - 100 ) /12]
Cpk = Min [0.8333 ; 0.8333]
Hence, Cpk = 0.8333