Answer:
$49,890
Step-by-step explanation:
The computation of the total amount of overhead costs assigned to the standard model is given below
The cost driver rate is
For setup
= $63,600 ÷ (11 + 29)
= 1,590
For component
= $102,600 ÷ (6 + 13)
= 5,400
Now the total amount of overhead for the standard model is
= 11 × 1,590 + 6 × 5,400
= $17,490 + $32,400
= $49,890
This is the answer but the same is not provided in the given options