Answer:
a. $81,610
b. $135,290
c. $117,200
d. $216,900
e. $252,490
f. $96,890
Step-by-step explanation:
direct labor cost = $83,600 - $1,990 = $81,610
manufacturing overhead cost = $28,700 + $1,990 + 31,400 + $31,600 + $13,600 + 28,000 = $135,290
prime cost = $35,600 + $81,610 = $117,200
conversion cost = $81,610 + $135,290 = $216,900
total manufacturing cost = $135,290 + $117,200 = $252,490
period expenses = $19,900 + $8,050 + $61,300 + $7,640 = $96,890