94,350 views
3 votes
3 votes
While using PERT (Program Evaluation Review Technique) and CPM (Critical Path Method) techniques, activities that are on the critical path are more flexible than those activities which are not on the critical path.

a. True
b. False

User Nery
by
2.6k points

1 Answer

13 votes
13 votes

Answer:

b. False

Step-by-step explanation:

The Critical Path Method(CPM) is used to determine the maximum time to finish a project based on the total maximum time of the network of interdependent activities in the project. The CPM is usually used in conjunction with the Program Evaluation Review Technique(PERT). If an activity is in the critical path then it is at its maximum or longest duration time and cannot be more flexible at this point.

User Luchnik
by
3.2k points