In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week.

WEEK NUMBER

ITEM J 0 1 2 3 4 5
Gross requirements 67 43 63
On-hand 46
Net requirements
Planned order receipt
Planned order release

User Louise Fallon
by
3.1k points

1 Answer

9 votes
9 votes

Answer:

Planned order receipts

Item 3 - 55

Item 4 - 74

Planned order releases

Item 2 - 55

Item 3 - 74

Step-by-step explanation:

Planned order receipts are the requirement for each item based on demand. Planned order releases is the finished goods processing time. When finished goods are ready, they are placed at warehouse for order dispatch.