MC Qu. 159 Copy Center pays an average wage... Copy Center pays an average wage of $11 per hour to employees for printing and copying jobs, and allocates $17 of overhead for each employee hour worked. Materials are assigned to each job according to actual cost. If Job M-47 used $300 of materials and took 20 hours of labor to complete, what is the total cost that should be assigned to the job

User Rene De La Garza
by
3.0k points

1 Answer

15 votes
15 votes

Answer:

$860

Step-by-step explanation:

Materials cost = $300

Labor cost = Labor hours * Wages per hour

Labor cost = 20 hours * $11

Labor cost = $220

Overhead cost = $17 * 20 hours

Overhead cost = $340

Total cost = Materials cost + Labor cost + Overhead cost

Total cost = $300 + $220 + $340

Total cost = $860

So, the total cost that should be assigned to the job is $860.