473,859 views
34 votes
34 votes
The painter contracts to paint the exterior of the home for $1,750 plus the cost of paint and any other necessary materials. About three-fourths of the way through the job, the contractor breaks his leg and can't finish. The owner offers to pay the contract price less deductions for the cost of having the job completed by another painter, and the original painter accepts the offer. The contract has been discharged under the principle of

User Jos Van Egmond
by
2.5k points

1 Answer

10 votes
10 votes

Answer:

substantial performance.

Step-by-step explanation:

From the question we are informed about painter which contracts to paint the exterior of the home for $1,750 plus the cost of paint and any other necessary materials. About three-fourths of the way through the job, the contractor breaks his leg and can't finish. The owner offers to pay the contract price less deductions for the cost of having the job completed by another painter, and the original painter accepts the offer. In this case, the contract has been discharged under the principle of substantial performance.

Substantial performance can be regarded as a term that is been

used as regards contract law, it is a principle that can be explained as

degree of performance of a contract that is not regarded as complete or full performance, but regarded as nearly equivalent which will be considered to be unfair if the contractor is denied the agreed payment in the contract.

User Csteinmueller
by
3.1k points