The project manager has brought the team together and they have introduced themselves to each other and learned about the project. After this the team starts to have disagreements about how the work on the project should be done. What stage of Tuckman ladder is the team currently in? a. Performing b. Forming c. Storming d. Adjourning

User Maaudet
by
8.6k points

1 Answer

3 votes
C.) Storming

This is the second part of Tuckman ladder. They still view themselves as individuals rather than a whole team. This creates disputes before teamwork