What is cost variance

User Eng
by
2.3k points

2 Answers

14 votes
14 votes

Answer:

Cost variance is the difference between the actual cost incurred and the planned/budgeted cost at a given time on a project.

Step-by-step explanation:

User Sivasubramanian
by
3.1k points
22 votes
22 votes
Cost variance is the difference between the actual cost and the planned or budgeted cost at a given time on a project.