Which of these best describes the Scrum approach to team-working?

Select one:
a. The team will "burn out" if they have to work overtime for more than two sprints in a row
b. The team should strive for a sustainable pace and a normal working week
c. The team should plan to work a small amount of overtime regularly throughout the project
d. The team should expect to work longer hours towards the end of the sprint, in order to deliver all that was committed to

1 Answer

5 votes

Final answer:

Scrum emphasizes a team should strive for sustainable work practices, avoiding overtime and burnout, ensuring a healthy work-life balance.

Step-by-step explanation:

The Scrum approach to team-working is best described by the idea that the team should strive for a sustainable pace and a normal working week. This philosophy is centered on maintaining a consistent work-life balance and avoiding burnout by not overburdening the team with excessive overtime. Contrary to traditional approaches that may demand longer hours towards the end of a project, Scrum emphasizes preserving the team's health and productivity through reasonable work schedules. Striving for a sustainable pace means the team should not be regularly working overtime or cramming at the end of the sprint to deliver committed tasks.