The critical chain approach can help prevent delays and even deliver a project earlier than with other approaches. Which choice is not part of the critical chain approach?

1) Identifying the critical path
2) Buffer management
3) Resource leveling
4) Agile project management

User Zmorris
by
7.6k points

1 Answer

0 votes

Final answer:

The critical chain approach includes identifying the critical path, buffer management, and resource leveling. Agile project management, which is iterative and emphasizes flexibility and customer collaboration, is not part of the critical chain approach.

Step-by-step explanation:

The critical chain approach is a project management technique that emphasizes the importance of resource management and buffer management to ensure that projects are completed on time. It involves several key components:

  1. Identifying the critical path, which is a sequence of stages determining the minimum time needed to complete a project.
  2. Buffer management, which refers to the creation of time buffers to protect the project timeline from delays.
  3. Resource leveling, which entails balancing the demand for resources by delaying tasks to manage resource constraints.

Agile project management is not part of the critical chain approach. Agile is a separate, iterative approach to project management and software development that emphasizes flexibility, customer collaboration, and rapid delivery of functional components. Therefore, the correct choice that is not part of the critical chain approach is Agile project management.