101k views
18 votes
Darius is putting tiles on the roof of his house. After working for 3 1/3 hours, he has completed 4/5 of the roof. Can Darius put the titles on the enitre roof in 4 hours if he continues to work at the same rate?

1 Answer

11 votes

Answer:

No.

Explanation:

It is given that Darius is putting tiles on the roof of his house.

Darius had completed =
$(4)/(5)$ th of the work

He takes time =
$3 (1)/(3)$ hours to complete
$(4)/(5)$ th of the work

The remaining work =
$1 -(4)/(5)$


$=(5-4)/(5)$


$=(1)/(5)$

∴ Darius completes
$(4)/(5)$ th of the work in =
$(10)/(3)$ hours

So,
$(1)/(5)$ th of the work in =
$(10)/(3) * (5)/(4) * (1)/(5)$ hours


$=(10)/(12)$ hours

Therefore total time taken to complete the work
$=(10)/(3)+(10)/(12)$ hours


$=(40+10)/(12)$ hours


$=(50)/(12)$ hours


$=4(2)/(12)$ hours


$=4(1)/(6)$ hours

Thus, Darius continues to work at the same rate will not be able to complete the work in 4 hours.

User Ian Drake
by
6.3k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.