Activity Descriptions:

A. Meet with board

Immediate Predecessor: None
Optimistic Time: 1 week
Most Probable Time: 1 week
Pessimistic Time: 2 weeks
B. Hire coaches

Immediate Predecessor: A (Meeting with the board)
Optimistic Time: 4 weeks
Most Probable Time: 6 weeks
Pessimistic Time: 8 weeks
C. Conduct fundraiser

Immediate Predecessor: A (Meeting with the board)
Optimistic Time: 2 weeks
Most Probable Time: 4 weeks
Pessimistic Time: 6 weeks
D. Announce program

Immediate Predecessors: B (Hire coaches) and C (Conduct fundraiser)
Optimistic Time: 1 week
Most Probable Time: 2 weeks
Pessimistic Time: 3 weeks
E. Unknown activity

Based on this information, let's analyze the schedule:

The initial activity is to meet with the board, which takes 1 to 2 weeks. This activity can be completed fairly quickly.

After meeting with the board, two parallel activities start: hiring coaches and conducting a fundraiser. Hiring coaches takes 4 to 8 weeks, while conducting a fundraiser takes 2 to 6 weeks. The timeline for these activities can vary significantly.

Once both hiring coaches and conducting a fundraiser are completed, the program can be announced. This step requires 1 to 3 weeks.

1 Answer

3 votes

Final answer:

The subject of this question is project management or scheduling. It involves organizing and coordinating activities in a specific order to achieve a desired outcome.

Step-by-step explanation:

The subject of this question is project management or scheduling. It involves organizing and coordinating activities in a specific order to achieve a desired outcome. In this case, the activities include meeting with the board, hiring coaches, conducting a fundraiser, and announcing the program.

The schedule provides information about the estimated time for each activity, including optimistic, most probable, and pessimistic times. It also identifies the dependencies between activities, where some activities cannot start until others are completed.

By analyzing the schedule, you can understand the sequencing and time estimates for each activity in the project.