Within a scrum, a sprint is a short time-boxed period of time. Which of the following would you classify as a "sprint"?

A. Daily meeting
B. Requirement gathering
C. Product launch
D. Two-week development iteration

User Latia
by
7.8k points

1 Answer

4 votes

Final answer:

In Scrum, a sprint is a set period for completing work, which can typically last from one to four weeks, with two weeks being common. Therefore, the correct answer is D. Two-week development iteration.

Step-by-step explanation:

Within a scrum, a sprint is defined as a short, time-boxed period where a team works to complete a set amount of work. Among the options provided, D. Two-week development iteration would be classified as a "sprint". Sprints are a core component of the Scrum framework in Agile methodologies, used for developing, delivering, and sustaining complex products.

A sprint often lasts between one to four weeks, with two weeks being a common duration. In contrast, a daily meeting (A) refers to the daily stand-up or scrum meeting, requirement gathering (B) is a part of product backlog refinement, and product launch (C) is an event that may occur after several sprints.