The correct action on the single line diagram, given the situation described, would be: B. Delete the AC disconnect and move the label of PV rapid shutdown to the breakers labeled as 6
What is the action'
The AHJ (Authority Having Jurisdiction) has requested the functionality of the PV rapid shutdown initiation device to be moved due to visibility concerns for firefighters.
Moving the label of the PV rapid shutdown to the breakers labeled as 6 would consolidate the functionality of the shutdown initiation device to the specified breakers.