Final answer:
No, the contractor is not relieved of responsibility for deviations from the requirements of the contract documents even if they receive an approved submittal from the architect.
Step-by-step explanation:
If the contractor receives an approved submittal by the architect is he relieved of responsibility for deviations from the requirements of the contract documents?
No, the contractor is not relieved of responsibility for deviations from the requirements of the contract documents even if they receive an approved submittal from the architect. The approved submittal simply means that the architect has reviewed and accepted the contractor's proposed materials, equipment, or methods. However, it does not absolve the contractor of their obligation to adhere to the contract documents and fulfill all the specified requirements.
For example, let's say the contract documents specify the use of a certain type of material for a construction project. If the contractor receives an approved submittal for a different type of material from the architect, it does not mean they can deviate from the specified material without consequences. The contractor is still responsible for following the requirements laid out in the contract documents unless there is a formal change order or written agreement that allows for a deviation.