Which of the following is NOT true about project stakeholders?

a. They are all individuals and organizations that are actively supportive of the project
b. They are all individuals and organizations actively involved in the project
c. They are all individuals and organizations whose interests may be affected as a result of project execution
d. They are all individuals and organizations that may exert influence over the project

1 Answer

3 votes

Final answer:

The statement that is NOT true about project stakeholders is that they are all individuals and organizations that are actively supportive of the project. Stakeholders can be affected by or have influence over a project without necessarily being supportive of it.

Step-by-step explanation:

Which of the following is NOT true about project stakeholders? The statement that is not true is: they are all individuals and organizations that are actively supportive of the project. Stakeholders may have various levels of engagement and interest in a project. While it is true that all stakeholders are individuals and organizations who may be affected by the execution of a project, that doesn't necessarily imply they actively support it. Stakeholders can include users, customers, the design team, the company that employs the design team, and broader groups such as government agencies, local businesses, and community members, all of whom have varying degrees of influence and interest in the project's outcome.