40.4k views
0 votes
480 persons working 10 hours per day complete one-fourth of a work in 10 days. how many additional persons are to be employed in order to complete the remaining work in 20 days, working 8 hours per day?

a) 400
b) 420
c) 480
d) 500

User KamilCuk
by
7.6k points

1 Answer

3 votes

Final answer:

To complete the remaining work in 20 days, working 8 hours per day, we need an additional 75 persons.

Step-by-step explanation:

To find the number of additional persons needed to complete the remaining work in 20 days, working 8 hours per day, we first need to calculate the amount of work done in 10 days by 480 persons working 10 hours per day. Since they completed one-fourth of the work, the total work done by them is 480 * 10 * 10 / 4 = 6,000 units.

Now, let's find the total work remaining. Since 6,000 units have been completed, the remaining work is 1 - 1/4 = 3/4 of the total work.

We can calculate the number of units completed in one day by 480 persons as 6,000 / 10 = 600 units. So, the total work remaining is 600 * 20 = 12,000 units. Since we want to complete this work in 20 days with 8 hours of work per day, we need to find the number of persons required.

Let's solve for the number of additional persons needed: 12,000 / (8 * 20) = 75 persons. Therefore, we need an additional 75 persons to complete the remaining work in 20 days.

User Vanetta
by
8.2k points