Final answer:
A, B, and C worked together for 13 days before A left the project.
Step-by-step explanation:
To find out how many days are from the start when A leaves the project, we need to calculate how many days it took for A, B, and C to complete a fraction of the project together. Let's assume the complete project is represented as 1.
So, the fraction completed by A, B, and C in one day is:
A: 1/10
B: 1/15
C: 1/20
When they worked together for a certain number of days, they completed a fraction of the project. Let's assume x is the number of days they worked together. So, the fraction completed by A, B, and C in x days is:
(1/10 + 1/15 + 1/20) * x
Given that the project was finished in 6 days, we can set up the equation:
(1/10 + 1/15 + 1/20) * 6 = 1
Simplifying the equation, we get:
(6/150 + 4/150 + 3/150) = 1
Therefore, they worked together for 13 days before A left the project.