148,198 views
9 votes
9 votes
Which of the following aspects of a work package are used by a work breakdown structure to facilitate planning, scheduling, and budgetary control?

1)Time estimates
2)technical performance requirements
3)resource requirements

User Hardik Joshi
by
3.1k points

1 Answer

22 votes
22 votes

Answer: if I’m not mistaken it’s 1 tell me if it’s wrong

Step-by-step explanation:

User Torsten Walter
by
2.8k points