A common activity for project managers is to ________ information from the project schedule to share with stakeholders.

a) Collect
b) Extract
c) Organize
d) Delete

1 Answer

2 votes

Final answer:

Project managers commonly extract information from project schedules to communicate important details to stakeholders. This ensures that all parties involved have a clear understanding of the project's status.

Step-by-step explanation:

A common activity for project managers is to extract information from the project schedule to share with stakeholders. This process involves identifying relevant details about project timelines, milestones, deliverables, and resources, and then summarizing this information in a clear and accessible format. Effective communication with stakeholders is critical to ensuring everyone involved in the project is informed and aligned on project objectives and progress.