Final answer:
Initial capacity planning involves estimating initial team capacity, adjusting for part-time employees and non-working days, and agreeing on a work standard using story points. Select actions include using eight points per person, subtracting points for non-working days, and defining a small user story as a baseline of one workday.
Step-by-step explanation:
An organization conducting their first PI Planning session will involve several steps to ensure an accurate capacity planning process. The initial stages of capacity planning for new agile teams generally include:
- Estimate initial team capacity by accounting for individual availability and potential velocity.
- Adjust for part-time employees and non-working days such as vacations, public holidays, and training days.
- Agree on a standard for what constitutes a certain amount of work, often using story points.
Key actions to be selected here could include:
- Use eight points per person (adjust for part-time employees).
- Subtract one point for every team member's vacation day, public holiday, or training day.
- Find a small story that takes about a day to develop and call it a one.
These steps help in setting realistic expectations and foster a consistent approach to workload distribution.