A Development Team selects a set of Product Backlog items for a Sprint Backlog with the intent to get the selected items "Done" by the end of the Sprint. Which three phrases best describe the purpose of a definition of "Done"? Choose 3 answers

A) Quality assurance
B) Acceptance criteria
C) Incremental progress
D) Customer satisfaction

User Cockscomb
by
7.2k points

1 Answer

4 votes

Final answer:

The purpose of a definition of 'Done' includes quality assurance, acceptance criteria, and evidencing incremental progress in a project. It ensures consistency in quality and aligns with stakeholder expectations for each Product Backlog item.

Step-by-step explanation:

The purpose of a definition of 'Done' in a Scrum or Agile environment ensures that the Development Team has a clear understanding of what it means for work to be completed on a Product Backlog item. This is crucial to maintain consistency, quality, and alignment with project goals. The three phrases that best describe the purpose of a definition of 'Done' are:

  • A) Quality assurance - Ensures that each Product Backlog item meets the necessary quality standards before being considered complete.
  • B) Acceptance criteria - Provides a list of conditions that a Product Backlog item must meet to be accepted by the stakeholders.
  • C) Incremental progress - Reflects the incremental nature of Agile development, where each completed item contributes towards the progress of the project.

While customer satisfaction is vital to a project's success, it is a broader goal that the definition of 'Done' supports indirectly through ensuring quality and meeting acceptance criteria, rather than being a direct component of the definition itself.